Roundabout

Overview

Rocklin Road and Pacific Street Roundabout

As the City of Rocklin continues to grow and develop, traffic on the Rocklin Road and Pacific Street corridors is anticipated to increase. The Rocklin Road and Pacific Street Roundabout Project will improve traffic operations and safety at the current four-way intersection.

An aerial rending of the Rocklin Rd. and Pacific St. roundabout


PROJECT LOCATION

The City will replace the existing four-way traffic signal at Rocklin Road and Pacific Street intersection with a two-lane roundabout.

The project limits will extend along Rocklin Road from Railroad Avenue to San Francisco Street, and on Pacific Street from Oak Street to Bush Street.

UPCOMING IMPROVEMENTS

In addition to the new roundabout, this project will:

  • Construct an oval-shaped, landscaped island at the center of the roundabout
  • Install a separate right turn lane outside of the roundabout for northbound and westbound approaches
  • Reconstruct all four approaches from the intersection
  • Replace concrete within the intersection with asphalt pavement
  • Improve underground utilities
  • Install new landscaping and street lighting

SCHEDULE

Major construction began on April 18, 2022 and is scheduled to be complete in Jan. 2023. Generally, construction will occur on weekdays, between 7 a.m. and 5 p.m.

STAY INFORMED

Sign up for project e-mail updates to learn about upcoming construction activities, anticipated impacts, and more.

SIGN UP HERE  


As the City of Rocklin continues to grow and develop, traffic on the Rocklin Road and Pacific Street corridors is anticipated to increase. The Rocklin Road and Pacific Street Roundabout Project will improve traffic operations and safety at the current four-way intersection.

An aerial rending of the Rocklin Rd. and Pacific St. roundabout


PROJECT LOCATION

The City will replace the existing four-way traffic signal at Rocklin Road and Pacific Street intersection with a two-lane roundabout.

The project limits will extend along Rocklin Road from Railroad Avenue to San Francisco Street, and on Pacific Street from Oak Street to Bush Street.

UPCOMING IMPROVEMENTS

In addition to the new roundabout, this project will:

  • Construct an oval-shaped, landscaped island at the center of the roundabout
  • Install a separate right turn lane outside of the roundabout for northbound and westbound approaches
  • Reconstruct all four approaches from the intersection
  • Replace concrete within the intersection with asphalt pavement
  • Improve underground utilities
  • Install new landscaping and street lighting

SCHEDULE

Major construction began on April 18, 2022 and is scheduled to be complete in Jan. 2023. Generally, construction will occur on weekdays, between 7 a.m. and 5 p.m.

STAY INFORMED

Sign up for project e-mail updates to learn about upcoming construction activities, anticipated impacts, and more.

SIGN UP HERE  


News
.JPG File of Roundabout Frequently Asked Questions Sheet

Rocklin Rd. and Pacific St. Roundabout Frequently Asked Questions

1. What is the total projected cost of the project and how is it funded?

The project is 100% funded by the Congestion Mitigation and Air Quality (CMAQ) Federal Grant, awarded to construction contractor George Reed for$4.46 million. No local funds are being used.

2. When will construction be complete?

The contractor has 180 working days to complete the project. With the official start on April 18, 2022, the project is scheduled to be completed by Jan. 5, 2023.

News
Video: Business Stakeholder Meeting Summary

Video: Business Stakeholder Meeting Summary

The Rocklin Road and Pacific Street roundabout project team hosted a virtual meeting on Sept. 29 to provide business stakeholders information about construction, which is scheduled to begin this fall, and answer logistical questions about the project.